|
The
History and Evolution of the Single Bore Multiple Anchor System
November
15, 1990 - Castrol (UK) Ltd news release "Wetherby company wins national award for research and development in construction industry"
"Wetherby based Keller Colcrete Ltd. has won the 1990 Castrol/Construction News Award for outstanding innovation in construction techniques, with an innovative flexible ground anchorage system, giving 50-150 per cent greater load capacity than traditional fixed anchor systems.The company accepted the award from Sir Clifford Chetwood, Chairman and Chief Executive of George Wimpey Plc, at a ceremony held at London's Savoy Hotel on 15th November."
November
22, 1990 - Construction News. "Anchor Breaks New Ground"
"Every
so often, an invention comes along which people will look at and
ask the question: "Why has no-one thought of it before?" But designing
the obvious: harnessing inovation with simplicity and efficiency
is the true mark of a mind with a fundamental understanding of a
problem." "...the
single bore multiple anchor system (SBMA) had its birth in the mind
of Keller Colcrete's contracts director, Tony Barley, some 10 years
before he found time to develop it.""By
any engineering standards, the SBMA is an impressive development.
It performs a routine application cheaper, more efficiently and
quicker than conventional techniques. It is a ground anchor system
which makes the ground do more of the work, with a resultant saving
both in time and money for client and contractor.""...SBMA
system has been shown to increase the load capacity of an equivalent
anchor site by at least 50 per cent, and as much as 150 per cent.
And fixed anchor lengths of up to 25m. have been successfully tested
with no evidence of redundancy."
December
13, 1990 - Construction News Supplement "In the Heart of Norwich"
"The...single
bore multiple anchor system is being used on the 7 acre Castle Mall
development (Norwich) right next door to the castle." "The
multiple anchors are being installed in six rows down the piling
wall with about 3m between each row.""Preliminary
test anchors achieved 1300 kNewtons without failure, acceptable
to the code of practice in BS8081."
May
30, 1991 - Construction News "How to Rout the Castle Crumble"
"Using
the patented single bore multiple anchor system that won the contractor
the Construction News R & D Award last year, Keller will
eventually drive and stress some 1,100 anchors through the retaining
wall."
June
17, 1993 - New Civil Engineer "Anchor advance."
"...single
bore multiple strand removable anchors can be destressed and withdrawn
from a grouted borehole after use, leaving behind just the grouted
column and small steel and plastic components." "Tendon
pull out forces are comparatively low, less than 50kN, eliminating
risk of strand breakage.""Keller
Colcrete has carried out trials in London Clay and in Hong Kong
granite. ...for the planned Jubilee Line extension ... These included
four and six strand anchors,which were proof loaded to 1300kN then
relaxed prior to the tendons being withdrawn.""In
the Hong Kong trials 12 strands with a 3m rock bond length were
loaded to 1600kN... A complete 26 strand, 28m long anchjor, using
12mm diameter tendons, was then tested to 2500kN, load released
and strands withdrawn."
April,
1994 - Ground Engineering "Tyneside weighs anchor"
"Of
the three SBMA trial anchors installed, two were overstranded to
allow testing to three times the 600kN working load on the designed
fixed length, while the third, constructed as a production anchor,
was installed for load loss testing." "Keller
loaded the overstranded anchors up to 2032kN with no indication
of failure, says Barley. While in the load loss test the anchor
was monitored for 10 days at 1.1 times working load (660kN) to ensure
load loss conformed to BS8081, which requires load loss over 10
days less than 8%. At Newcastle only 3% was lost and when loaded
to 900kN for 24 hours, load loss was still only about 3%.""Anchor
lengths are up to 35m as the anchors pass, in free length form,
through up to 15m of placed fill before encountering till."
November
24, 1994 - New Civil Engineer "Multiple Choice"
"...a
couple of drilling crews ... are installing what are said to be
the highest loaded ground anchors yet designed." "Yet,
impressive as working loads of 950kN are, contractor Keller Colcrete's
engineering director Tony Barley claims the record will not last
long. "Given suitable ground conditions, there is no reason why
we cannot achieve working loads of 2000kN and ultimate loads approaching
5000kN," he says.""The
63 sets of ground anchors now being driven an average 45m into the
steep sloping riverside site..."
November
30, 1995 - Construction News "Support takes a load off your mind."
"But
using the SBMA system, the firm achieved a jump in the working load
to between 50 and 115 tonnes. And Keller hasn't stopped there. "One
year ago we were getting an ultimate load of 240 tonnes," says Mr
Barley. "Now it is 360 tonnes."
January/February
1996 - Ground Engineering "Removable anchor test succeeds."
"A
further two anchors were installed in completely decomposed granite
.... achieved in excess of 2000kN without failure .." "On
completion of the tests, 54 of the 56 prestressing strands were
fully removed from the 30m to 40m long anchor bores by simple jacking
and winching."
March
1997 - Ground Engineering "Heavy loads ahead."
"New
records for high capacity anchors in soils have been established
at the new Hong Kong station ... Working loads of 2000kN have been
achieved, ..." "...further
pre-production testing was needed to verify the design and system
at these loads.Tests
carried out ... achieved in excess of 3000kN without failure, confirming
that 2000kN working load anchors were safely within the system's
capabilities. Trial anchors also demonstrated complete removal of
the tendons.
June,
1998 - Ground Engineering "Anchors take the load on Northampton clay."
"The
working SBMA anchors, each around 25m long, were installed at high
levels on the wall as piling progressed, and were stressed once
the capping beam was finished. A trial anchor was installed before
the main works, confirming that a final design load of 750kN per
anchor could be used in the Lias Clay."
November,
1998 - Ground Engineering "Multiple anchors set load record."
"Working
loads on the SBMAs are 1300kN, .... the highest ever achieved in
permanent works anchors founded in such fine grained soils as the
Bracklesham Beds - stiff to hard silty, sandy clay and claybound
sand." "Two
test anchors proved it when they were taken to 2.5 times the working
load (up to 3250kN)."
January,
2000 - Ground engineering "Man of the moment."
"All
other anchor systems are designed to found the entire anchor in
a single stratum and thus normal systems could not have accommodated
the variation in the encountered ground nor provided 900kN working
load when founded in one of the relatively thin soil materials,..."
2000 onwards.
Further developments of the SBMA system are documented on the 'Stop Press' page.
|