Case Histories

Design and Construction of an Anchored Bored Pile Wall at the Pinnacles, Northampton
The design and construction of an anchored bored pile wall in Upper Lias Clay to retain a site boundary for a new commercial/retail development.
Project
As part of the construction of a new commercial/retail development, a 180m lenght of the site boundary required to be retained to a maximum height of 8m. Maximisation of development space was a key criteria. Accordingly, Keller Ground Engineering designed and built a permanently anchored bored pile wall complete with reinforced concrete capping beam. By utilisation of the patented SBMA anchor system, the number of ground anchors was significantly less than using conventional systems.

Soil Conditions
Ground information on the site showed topsoil overlying Upper Lias Clay (stiff to very stiff silty clay).

Solution
This consisted of 600mm bored piles at 750mm centres with an associated capping beam. To prop the wall through the capping beam, ground anchors were proposed to retain a horizontal force of 140kN per metre run using permanent SBMA anchors at 4.5m centers. The design working load for the anchors was 730kN within the till.
A preliminary trial anchor was tested up to a maximum load of 2280kN to demonstrate the grout/ground bond properties. This allowed detailed design of the working anchors to be completed.

Construction
The bored pile wall was installed using CFA piling methods. The capping beam construction immediately followed. Once the beam was installed ground anchors were formed using rotary duplex drilling methods. All anchors were successfully tested at the required test load.

 
Client Wrenbridge (Brackmills) Ltd.
Engineer Tapsell Wade & Partners
Main Contractor Marriot Construction Ltd.
Specialist Sub-contractor Keller Ground Engineering

 

Home | Technical Info. | History | Technical Papers | Case Histories | Contact us