Case Histories

Flood Prevention by the use of Sheet piles and Permanent Ground Anchors on the Norfolk Broads
Permanent Single Bore Multiple Anchors (S.B.M.A.) were installed to new sheet pile walls. The site is an area of protected status requiring minimum environmental impact.
Project
The Environment Agency's Broadland Strategy aims to reduce the risk of flooding along almost 240 km of river bank. At the Berney Arms and Reedham Ferry sites protected land plus a bird sanctuary gave severe problems to the Client in the reconstruction of the river wall. The original retention scheme consisted of tie bars at close centers along the wall which was unacceptable to the various authorities.

Soil Conditions
Ground conditions behind the walls consisted of thick deposits of very soft alluvium overlying a medium dense fine sand deposit with interbedded clay bands.

Solution
To minimise disruption to the surroundings, Keller Ground Engineering proposed to use a high capacity ground anchor alternative with SBMA anchors at maximum spacings.
This allowed anchors to be installed at 4.8m centres producing a cost effective solution. In all 117 No, 600kN anchors were installed at Berney Arms Reach and 160 No. were installed at Reedham Ferry. To confirm the design assumptions, two trial anchors were tested up to 1200kN without failure.

Construction
All plant and materials were brought in by boat. Drilling and installation took place from a specially designed cantilever platform. The anchors were installed using rotary percussive drilling methods with flush returns carefully controlled within a sump consisting of the gap between the old and new piles. All anchors were successfully test loaded to BS8081 standards.

 
Client Environment Agency
Engineer Sir William Halcrow & Partners
Main Contractor Tilbury Douglas Construction Ltd.
Specialist
Sub-contractor
Keller Ground Engineering

 

Home | Technical Info. | History | Technical Papers | Case Histories | Contact us