Case Histories

Case History

Permanent and Temporary Ground Anchors at Welmore Lake Sluice, Downham Market
As part of the permanent and temporary works, Single Bore Multiple Ground Anchors (S.B.M.A.) were used to support one of the largest circular sheet pile cofferdams constructed in Europe.
Project
As part of the construction of Welmore Lake Sluice, the scheme required permanent propping of the two wing walls together with the temporary propping of half of a circular cofferdam wall. Both the permanent and temporary props required high loads, which were initially believed to be unsuitable for conventional ground anchors. The original scheme was therefore based on the use of tie rods and internal propping.

Soil Conditions
The ground conditions consisted of soft alluvium overlying firm becoming very stiff sandy clay with chalk gravel (glacial till).

Solution
After a detailed study of the conforming propping scheme, Keller proposed an alternative ground anchor scheme comprising temporary SBMA anchors with working loads up to 925kN for the cofferdam and permanent SBMA anchors to the wing walls. To prove the ground anchor design proposed, 2 trial anchors were installed within the cofferdam, and were tested up to 2000kN without failure (over twice the working load)

Construction
All ground anchors within the cofferdam were constructed using a Keller SM400 machine, with anchors on the wing wall constructed using a Keller long reach machine specially converted to allow under-slung drilling from an off-shore platform. The boreholes were formed using rotary duplex drilling systems wiht anchor lengths from 30 to 40 metres. All ground anchors were successfully tested to 1.5 x working load specified by BS8081.

 
Client Environment Agency
Engineer Lewin Fryer Partners
Main Contractor Jackson Civil Engineering Ltd.
Specialist Sub-contractor Keller Ground Engineering

 

Home | Technical Info. | History | Technical Papers | Case Histories | Contact us