Case Histories

Permanent Ground Anchors to the Camber Quay Docks at Portsmouth
High capacity Single Bore Mutiple Anchors installed at twice the spacing of the proposed tie rods, provided a distinct economic saving and eliminated the necessity to demolish a number of structures.

Project

As part of the structural upgrade of the Camber Dock, a new sheet pile wall required supporting over a 236m lenght of wall.

The client originally proposed a tie bar system, which involved the demolition of a fisherman's store structure to allow trenching and installation of the tie rods and driving of rear pile wall.

Soil Conditions
The geology behind the existing quay wall consisted of fill and marine deposits overlying Bracklesham Beds. This main stratum was stiff to hard silty sandy Clay and clay-bound sand. Additional complications included the presence of old retaining walls buried behind the existing quay side structure.

Solution
Keller Ground Engineering proposed high capacity ground anchors at 4m spacings along the wall. This demanded a working load of up to 1300kN per anchor, probably the highest permanent anchor working load used in a stiff to hard sandy clay stratum. Such loading is only possible due to the SBMA efficiency in using ground strength over a multiple of anchor unit fixed lengths totalling 25m. An additional complication arose from the problem of anchor interference due to the curvature of the wall layout.

The complex anchor arrangement, utilising anchors at a variety of inclinations, was prepared using Autocad systems. The construction of the final anchor layout demended precision in set-up and drilling control and monitoring in both directions with minimal borehole deviation. Test anchors were installed and tested up to 2.5 times the working load (3250kN) to ensure satisfactory performance of the designed anchors.

Construction
All ground anchors were installed using Keller's specially converted machines for under-slung drilling. Despite the severity of the drilling difficulties in penetrating a muLtiple of existing barriers (concrete, masonry and steel) all anchors were installed successfully and no unacceptable deviations occurred causing anchor interference.

Client and Engineer Portsmouth City Council
Main Contractor J T Mackley Ltd.
Specialist Sub-contractor Keller Ground Engineering

 
Home | Technical Info. | History | Technical Papers | Case Histories | Contact us